When is a blower door test done on a Vancouver build?
When is a blower door test done on a Vancouver build?
A blower door test is done at the airtightness verification stage of construction — typically after the building envelope is complete and sealed, but before interior finishes cover the air barrier.
In practical terms, this means the test happens once your insulation and air barrier (poly, spray foam, or membrane) are installed, all penetrations (electrical, plumbing, HVAC) are sealed, windows and doors are in, but drywall may or may not be up depending on your energy modeller's preference. Many builders do a pre-drywall test so that any air leakage failures can still be fixed without tearing out finished walls — this is strongly recommended.
For BC Energy Step Code compliance, the blower door test is a mandatory part of the as-built energy compliance process. Your energy advisor (a registered EnerGuide energy advisor through Natural Resources Canada) will conduct the test and produce the final compliance report that your building department requires before occupancy. Without a passing result, you won't get your occupancy permit. The test depressurizes the building to 50 Pascals and measures air changes per hour (ACH50) — the target varies by Step Code level, but Step 3 (the current baseline for most Metro Vancouver municipalities) requires ≤ 3.0 ACH50 for Part 9 residential buildings.
Timing within the project schedule typically looks like this: framing inspection → insulation and air barrier installed → blower door test (pre-drywall preferred) → any remediation if needed → drywall and finishes → final inspection → occupancy permit. Some builders do a second confirmatory test after drywall just to be sure, though only the final as-built test is submitted for compliance.
Vancouver-specific context: As of March 10, 2025, all new permit applications must comply with BCBC 2024, which also introduced the new Zero Carbon Step Code EL-1 requirements — meaning your energy modelling package now needs to address both energy efficiency and operational greenhouse gas emissions. Your energy advisor should be handling both. Some municipalities like the City of Vancouver and the City of North Vancouver have historically required higher Step Code levels than the provincial minimum, so confirm your local requirements with your building department before finalizing your energy design.
Who does the test? A registered energy advisor — not your general contractor, not a home inspector. Your GC should be coordinating the test timing with the energy advisor, ideally scheduling it into the construction schedule well in advance. Last-minute bookings are common and can delay your project if advisors are booked out.
If you're building in Metro Vancouver, browse the Vancouver Construction Network directory to find experienced builders and energy consultants familiar with local Step Code compliance requirements.
Construction Brain — Built by a licensed contractor with 20+ years in the field. Powered by AI with strict guidelines and real building knowledge.
Ready to Start Your Project?
Get a free, no-obligation estimate for your Vancouver renovation. Our team at VCN is ready to help bring your vision to life.