How long does the permit process take in Burnaby compared to Vancouver?
How long does the permit process take in Burnaby compared to Vancouver?
The City of Burnaby has maintained more efficient permit processing times, typically requiring 3-6 weeks for standard residential renovations like kitchen and bathroom remodels, basement finishing, and secondary suite conversions. More complex projects involving structural changes or new construction may take 6-10 weeks. Burnaby's building department at 604-294-7130 has streamlined their review process and generally provides more predictable timelines.
Burnaby's permit process is generally faster than Vancouver's, with most residential permits taking 3-6 weeks compared to Vancouver's notoriously slow 6-12+ weeks for similar projects.
Vancouver's permit delays have become legendary among contractors and homeowners. Simple residential permits that should take 4-6 weeks often stretch to 8-12 weeks or longer. Kitchen renovations, bathroom remodels, and basement finishing permits frequently face delays due to staff shortages and an overwhelming application volume. Complex projects involving heritage properties, character home renovations, or new laneway houses can take 4-6 months or more. The City of Vancouver (604-873-7000 or vancouver.ca/home-property-development/building-permits) has acknowledged these delays and is working to improve processing times, but progress has been slow.
Why the difference? Vancouver processes roughly 10 times more permit applications than Burnaby, creating bottlenecks in their system. Vancouver also has more complex zoning requirements, heritage considerations, and design review processes that add time. Burnaby's building department has maintained adequate staffing levels relative to their application volume, while Vancouver has struggled with staff retention and training.
Planning your timeline: If you're renovating in Burnaby, budget 4-8 weeks from application to permit issuance for most residential projects. In Vancouver, budget 10-16 weeks minimum and don't be surprised if it takes longer. Both municipalities offer pre-application meetings to identify potential issues early - this investment of time upfront can prevent delays later.
Pro tip: Submit complete, professionally-prepared drawings and applications. Incomplete submissions get rejected and go to the back of the queue. Many contractors now build 12-16 weeks of permit time into Vancouver project schedules, while Burnaby projects can often start within 6-8 weeks of application.
---
Find a General Contractors Contractor
Vancouver Construction Network connects you with experienced contractors in the directory:
Browse all contractors →Construction Brain — Built by a licensed contractor with 20+ years in the field. Powered by AI with strict guidelines and real building knowledge.
Ready to Start Your Project?
Get a free, no-obligation estimate for your Vancouver renovation. Our team at VCN is ready to help bring your vision to life.