How do I plan a kitchen renovation around my family's daily routine?
How do I plan a kitchen renovation around my family's daily routine?
Planning a kitchen renovation around your family's daily routine requires setting up a temporary kitchen, scheduling work phases strategically, and preparing for 6-12 weeks of disruption. The key is creating realistic expectations and backup plans for meals, homework, and daily activities.
Establish a Temporary Kitchen Setup
Before demolition begins, create a functional temporary kitchen in your dining room, basement, or garage. You'll need a mini-fridge, microwave, electric kettle, slow cooker, and basic prep space with a cutting board. Stock up on paper plates, disposable utensils, and easy-to-prepare meals. Many Vancouver families set up camp in their basement recreation room or convert a spare bedroom into a temporary food prep area. This setup will be your lifeline for 2-3 months, so invest in making it as functional as possible.
Phase the Work Around School and Work Schedules
The most disruptive phases are demolition (1-2 weeks) and drywall/painting (2-3 weeks) due to dust and fumes. Schedule these during school breaks if possible, or plan for family members to stay elsewhere during the worst phases. In Metro Vancouver's competitive renovation market, book your contractor 3-6 months ahead to secure timing that works for your family. Many contractors prefer starting major kitchen projects in late spring or early summer when weather allows for better ventilation and outdoor meal preparation.
Plan for Extended Timelines
Vancouver kitchen renovations typically take 8-12 weeks due to permit processing delays, material lead times, and inspection scheduling. Factor in potential delays for custom millwork (very popular in Vancouver's high-end market), appliance delivery, and city inspections. Electrical and plumbing rough-in work requires licensed contractors and Technical Safety BC inspections, which can add 1-2 weeks to your timeline. Budget an extra 20-30% buffer time beyond your contractor's initial estimate.
Meal Planning and Daily Routines
Stock your temporary kitchen with breakfast essentials, lunch-making supplies, and simple dinner options. Invest in meal delivery services during the most disruptive weeks, or plan to eat out more frequently (budget $200-400/week extra for a family of four). Set up homework and charging stations away from construction dust. If you have young children, arrange playdates or activities outside the home during the loudest work hours (typically 8am-4pm in most Vancouver neighbourhoods).
Strata Considerations
If you live in a condo or townhouse, review your strata bylaws before starting. Most Vancouver stratas restrict construction to weekdays 8am-5pm and require contractor insurance, damage deposits, and advance notice to neighbours. Some buildings have specific requirements for dust containment and debris removal that could affect your renovation timeline and budget.
Working with licensed pros
A kitchen renovation involves electrical, plumbing, and potentially structural work that requires licensed professionals. Start by getting quotes from 3-4 contractors who can walk you through the entire process and help you understand realistic timelines. The investment in proper planning upfront will save you stress and unexpected costs during the renovation process.
Construction Brain — Built by a licensed contractor with 20+ years in the field. Powered by AI with strict guidelines and real building knowledge.
Ready to Start Your Project?
Get a free, no-obligation estimate for your Vancouver renovation. Our team at VCN is ready to help bring your vision to life.